6.2 Simulation Model Details
163
information technology systems that are based on a common time stamp and can
thus be merged automatically.
6.2
Simulation Model Details
The simulation model as well as the optimization experiments are created in AnyLogic PLE 8.5.1. As already for the fictional case study, the simulation model is
built using the three different simulation paradigms. The data from the real production is used for the model. Quantities, processing times, maintenance plans,
buffer sizes, and delivery schedules are set according to the real production scenario. The machine logic types have already been modeled for the fictious case
study and can be used via drag and drop for every model including all optimization parameters and restrictions described in sections 5.6.2 and 5.6.3. The
modeling of the Bosch simulation model as well as the setup of the optimization
experiments is—in large parts—similar to the procedure in the fictional case study.
Deviations caused by the special production situation (strongly linked production
machines) are described in the following sections.
Figure 6.5 Machine logic and switching options of the Bosch production machines
163
information technology systems that are based on a common time stamp and can
thus be merged automatically.
6.2
Simulation Model Details
The simulation model as well as the optimization experiments are created in AnyLogic PLE 8.5.1. As already for the fictional case study, the simulation model is
built using the three different simulation paradigms. The data from the real production is used for the model. Quantities, processing times, maintenance plans,
buffer sizes, and delivery schedules are set according to the real production scenario. The machine logic types have already been modeled for the fictious case
study and can be used via drag and drop for every model including all optimization parameters and restrictions described in sections 5.6.2 and 5.6.3. The
modeling of the Bosch simulation model as well as the setup of the optimization
experiments is—in large parts—similar to the procedure in the fictional case study.
Deviations caused by the special production situation (strongly linked production
machines) are described in the following sections.
Figure 6.5 Machine logic and switching options of the Bosch production machines