1.2.8.1.5.1.2.1 F ailure to assign required
resources
1.2.8.1.5.1.2.2 L ack of available resources
1.2.8.1.5.1.3 Cost
1.2.8.1.5.1.3.1 T otal cost exceeds budgeted
cost
1.2.8.1.5.1.3.2 R ate of expenditures exceeds
cash flow constraints
1.2.8.1.5.2 Implement practices to identify risks
1.2.8.1.5.2.1 Establish risk management board
1.2.8.1.5.2.2 Checklists for project risk areas
1.2.8.1.5.2.3 L essons learned from previous projects
1.2.8.1.5.2.4 Resource availability lists
1.2.8.1.5.2.5 R esource training records for applicable
skills
1.2.8.1.5.2.6 Peer review of project plans
1.2.8.1.5.2.7 S enior management review of project
plans
1.2.8.1.5.3 Document all risks captured during definition and
risk identification
1.2.8.1.6 Assess
1.2.8.1.6.1 Estimate probability of occurrence of each risk
event identified
1.2.8.1.6.2 E stimate the consequences of the occurrence of
each risk event
1.2.8.1.6.2.1 E stimate the impact on technical solution
(measured in terms of impact on s chedule
and/or cost)
1.2.8.1.6.2.2 E stimate the impact on schedule (mea
sured in terms of extra time required to
complete the project)
1.2.8.1.6.2.3 E stimate the impact on cost (measured in
terms of dollars)
1.2.8.1.6.3 V isualize risk assessments for technical solu
tion, schedule, and cost using two-dimensional
plots
1.2.8.1.6.3.1 Plot risk probabilities along the y-axis
1.2.8.1.6.3.2 Plot risk consequences along the x-axis
1.2.8.1.6.4 Categorize assessments based on data plots
1.2.8.1.6.4.1 “High” risks have the greatest
consequences
1.2.8.1.6.4.2 “ Medium” risks have less impact on the
project than high risks
1.2.8.1.6.4.3 “Low” risks have the least impact
327
Appendix 1: “To Manage” Decomposition
resources
1.2.8.1.5.1.2.2 L ack of available resources
1.2.8.1.5.1.3 Cost
1.2.8.1.5.1.3.1 T otal cost exceeds budgeted
cost
1.2.8.1.5.1.3.2 R ate of expenditures exceeds
cash flow constraints
1.2.8.1.5.2 Implement practices to identify risks
1.2.8.1.5.2.1 Establish risk management board
1.2.8.1.5.2.2 Checklists for project risk areas
1.2.8.1.5.2.3 L essons learned from previous projects
1.2.8.1.5.2.4 Resource availability lists
1.2.8.1.5.2.5 R esource training records for applicable
skills
1.2.8.1.5.2.6 Peer review of project plans
1.2.8.1.5.2.7 S enior management review of project
plans
1.2.8.1.5.3 Document all risks captured during definition and
risk identification
1.2.8.1.6 Assess
1.2.8.1.6.1 Estimate probability of occurrence of each risk
event identified
1.2.8.1.6.2 E stimate the consequences of the occurrence of
each risk event
1.2.8.1.6.2.1 E stimate the impact on technical solution
(measured in terms of impact on s chedule
and/or cost)
1.2.8.1.6.2.2 E stimate the impact on schedule (mea
sured in terms of extra time required to
complete the project)
1.2.8.1.6.2.3 E stimate the impact on cost (measured in
terms of dollars)
1.2.8.1.6.3 V isualize risk assessments for technical solu
tion, schedule, and cost using two-dimensional
plots
1.2.8.1.6.3.1 Plot risk probabilities along the y-axis
1.2.8.1.6.3.2 Plot risk consequences along the x-axis
1.2.8.1.6.4 Categorize assessments based on data plots
1.2.8.1.6.4.1 “High” risks have the greatest
consequences
1.2.8.1.6.4.2 “ Medium” risks have less impact on the
project than high risks
1.2.8.1.6.4.3 “Low” risks have the least impact
327
Appendix 1: “To Manage” Decomposition
