Installation of a Brown Field Slag Reduction Furnace: State …
199
Process Results
The plant was commissioned in summer 2018, and FAC was received still in 2019.
The Kuettner design features together with the LUEHR off-gas filter proved to
operate as designed.
Compared to traditional SBF installations, the Kuettner SBF off-gas treatment
concept provided a strong improvement in terms of safe and accretion-free operation
of the boiler inlet and top.
The key achievements were as follows:
– Stable operation with respective design throughput
– Full post-combustion and safe operation
– No accretion formation of sticky dust in the boiler top
– The required low emission level criteria were achieved without the need for wet
scrubbers.