tion of the dredging operations in order to keep the spillage percentages below prescribed maximum limits in time and space.
10.5.3
Dredging Operations
The construction work for the 0resund Link involves dredging of approximately
7 million m 3 material from the seabed. The overall requirement states that the total
average spillage from dredging operations must not exceed 5% (Ministry of Transport
and Ministry of Environment and Energy 1995). The dredging and reclamation work is
divided into a number of sub-operations (Fig. 10.1). A dredging instruction and a spill
budget for the work have to be approved by the environmental authorities before each
sub-operation starts. The dredging instructions lay down the detailed guidelines for
the extraction work.
Fig. 10.1. Approved extraction areas as at 31 December 1996. Areas for individiual dredging instructions (Nr.1-9) are indicated by arrows. CDl , CD3-1 and CD4 show position of compensation dredging
areas. (Modified from 0resundskonsortiet 1997)