H. Michino and T. Koji
28.3.6 Profit Calculation
In conculution of calculation, profit is just difference between sales and cost. We
conducted economic assessment for different size of palm oil mills in each case.
Minimam capacity of FFB treatment is 10 t/h and we calculated at each capacity
increased by 10t/h umtil 100t/h.
28.4 Result
28.4.1 Cost Calculation
Cost calculation The result of construction cost is shown in Fig. 28.3. It discrives that
the initial cost of case 6 which is the common system of the actual situation (only
MF is utilized) is the lowest.
The result of transportation cost is shown in Fig. 28.4. In this figure, transportation
cost in each case at the palm oil mill whose capacity is 50t/h. From result of both
Fig. 28.3 Construction cost
Fig. 28.4 Transportation
cost (at 50 h/t palm oil mill)
H. Michino and T. Koji
28.3.6 Profit Calculation
In conculution of calculation, profit is just difference between sales and cost. We
conducted economic assessment for different size of palm oil mills in each case.
Minimam capacity of FFB treatment is 10 t/h and we calculated at each capacity
increased by 10t/h umtil 100t/h.
28.4 Result
28.4.1 Cost Calculation
Cost calculation The result of construction cost is shown in Fig. 28.3. It discrives that
the initial cost of case 6 which is the common system of the actual situation (only
MF is utilized) is the lowest.
The result of transportation cost is shown in Fig. 28.4. In this figure, transportation
cost in each case at the palm oil mill whose capacity is 50t/h. From result of both
Fig. 28.3 Construction cost
Fig. 28.4 Transportation
cost (at 50 h/t palm oil mill)