Annexes III Template for a Biofouling Management Plan (United Kingdom)
XV
Biofouling management action plan to minimise the transfer of invasive aquatic species
Ship area
(To be completed for areas particularly susceptible to biofouling – see
previous)
Planned management action and frequency
(e.g., inspections, cleaning, repairs and maintenance)
Management action if ship operates outside its
usual operating profile
Hull
Vertical
Flat-bottom
Docking block positions
[Variation in block plan between dockings / bouncing the ship in the dock /
in-water cleaning before / after docking / routine in-water cleaning]
Boot-top
Bow dome
Hull appendages and fittings:
Bilge keels
A-brackets
Stabilizer fins
CP anodes
Steering, propulsion and positioning:
Propellers
Stern tube seal
Rope guards
Précédent

La biosalissure « biofouling » de la coque des navires, une menace pour la biodiversité du milieu marin - 191/217

Suivant