Interview with Patrick Bernhardt
Offshore Site Installation-Manager
The industrial superviser coordinated the so-called offshore site management before and during the
installation phase of Butendiek. He joined wpd offshore solutions in 2011 and before that spent seven
years with an offshore turbine manufacturer in Bremerhaven. He was part of the installation crew who
was involved to install the first German offshore wind farm, alpha ventus.